12.0220 Delivery point-Defined-Approval-Multiple occupancy.

Cite as [A.S.A.C. § 12.0220]

(a) The delivery point is the point where the utility’s drops attach to the building. The delivery point must be in clear view of a power pole. The delivery point must be approved by the utility before building wiring is installed. Thc utility shall not own or maintain any facilities beyond the delivery point except for the meter.

(b) The utility will provide only 1 delivery point per building. Where the building provides for multiple occupancy, the 1 service per building must supply all meters for all tenants in the building. The meters shall be grouped or ganged at 1 central point.

History: Rule 4-80, eff 1 Apr 80, Delivery Point.