25.0403.8 As-Built Drawings.

Cite as [A.S.A.C. § 25.0403.8]

(1) A registered professional engineer shall clearly and accurately record or mark, on a complete set of project engineering drawings, each deviation from the original drawings and specifications and the dimensions of the deviation. The set of marked drawings becomes the As-Built drawings, reflecting the project as actually built.

(2) A registered professional engineer shall sign, date, and place the engineer’s seal on each sheet of the As-Built drawings and submit them to AS-EPA upon completion of the project. The As-Built drawings shall be accompanied by an Engineer’s Certificate of Completion, signed by the registered professional engineer.

History: Rule 1-08, eff 1 Jun 08.